Administration Attorney Communities that Care Community Development / Public Works Economic Development Engineering Finance Fire Department Human Resources Library Parks & Recreation Police Department Recorder
My Account Renew My Items Downloadables Events & Programs at My Library About My Library Ask-a-Librarian Social Media
Select Page

Updated July 21, 2021

S.R. 112 PROJECT UPDATE

Paving work on S.R. 112 is nearing completion! Thank you for your patience during this pavement renewal project. Crews are continuing to head westbound on S.R. 112 and are on schedule to finish paving in the coming weeks.

One-way flagging operations are in place between 7 a.m. and 10 p.m. Drivers can expect up to 15-minute delays when traveling through the area. Drivers are encouraged to use alternate routes such as S.R. 138 and S.R. 36. Work is expected to continue through the summer.

S.R. 138 PROJECT UPDATE

Paving work on S.R. 138 is now complete. Brief, intermittent lane closures for utility work are scheduled to occur during non-commute times between 8 a.m. and 4 p.m. Signage installation, shoulder work and installation of centerline rumble strips along certain areas of the roadway are also scheduled to occur this week. Drivers can expect minor delays when traveling through the area.

PROJECT INFORMATION

UDOT is dedicated to investing in the community by renewing the pavement on S.R. 138 and S.R. 112. This work will improve safety, reduce traffic-related noise and provide a more enjoyable ride for all area residents and businesses.

Paving work is now complete on S.R. 138. Paving is currently underway on S.R. 112. Lane restrictions on S.R. 112 will take place between 7 a.m. and 10 p.m. One lane will be open to one direction of travel at a time, with one-way flagging operations. Drivers can expect delays and travel on uneven pavement surfaces.

Area residents and businesses can expect temporary intermittent closures of side streets as paving work passes through the area. Travelers, area residents, and businesses can expect construction-related noise, dust, and minor travel delays.

CONTACT US:

Questions? Concerns? Our dedicated public involvement team is here to help. Please feel free to call the project hotline at (435) 213-1637 or email us at SR112andSR138@utah.gov. In addition, check the project websites for more information: udot.utah.gov/go/sr138 | udot.utah.gov/go/sr112

Stay up to date with upcoming construction projects in the area by following the UDOT Tooele Valley Construction Projects Facebook page.

Please note that construction schedules are subject to change due to weather or equipment-related issues.


Updated July 7, 2021

A FULL closure of S.R. 112 (1000 North) between Utah Ave. and S.R. 36 is scheduled to start at 5 a.m. on Friday, July 9 and continue until 5 a.m. on Monday, July 12. Due to equipment-related delays, the previously scheduled closures were rescheduled to these new dates. Please refer to this map for alternate routes during the closure.

SR112 Closure Map

UDOT is working to improve mobility on State Route S.R. 112 for all users of the transportation system. As part of the pavement renewal project, the project team is up grading the pavement at two intersections on S.R. 112. These needed up grades will extend the life of the pavement and improve safety in the area.  This pavement renewal project will improve safety, extend the life of the roadway, reduce traffic-related noise, and provide a more enjoyable ride for roadway users.

One-way flagging operations will be in place during paving operations. Drivers can expect up to 15-minute delays when traveling through the area and are encouraged to use alternate routes such as S.R.138, and S.R. 36. Work is expected to continue through the summer.

CONTACT US

Questions? Concerns? Our dedicated public involvement team is here to help. Please feel free to call the project hotline at (435) 213-1637 or email us at SR112andSR138@utah.gov. In addition, check the project websites for more information: udot.utah.gov/go/sr138 | udot.utah.gov/go/sr112

Stay up to date with upcoming construction projects in the area by following the UDOT Tooele Valley Construction Projects Facebook page.

Please note that construction schedules are subject to change due to weather or equipment-related issues.


S.R. 112 PROJECT UPDATE

Updated June 28, 2021

Paving work on S.R. 112 is scheduled to begin the morning of Monday, June 28 at the S.R. 138/S.R. 112 intersection. One-way flagging operations will be in place between 7 a.m. and 10 p.m. Drivers can expect up to 15-minute delays when traveling through the area. Drivers are encouraged to use alternate routes such as S.R. 138 and S.R. 36. Work is expected to continue through the summer.

**UPDATED CLOSURE INFORMATION**

Due to equipment-related delays, the closure of the S.R. 112/600 W. intersection will be rescheduled to a later date. More information will be included in next week’s email update. 

 

S.R. 138 PROJECT UPDATE

Paving work on S.R. 138 is now complete. Brief, intermittent lane closures for permanent striping, utility work and signage installation are scheduled to occur on weekdays during non-commute times between 8 a.m. and 4 p.m. Drivers can expect minor delays when traveling through the area.

 

PROJECT INFORMATION

UDOT is dedicated to investing in the community by renewing the pavement on S.R. 138 and S.R. 112. This work will improve safety, reduce traffic-related noise and provide a more enjoyable ride for all area residents and businesses.

Paving work is now complete on S.R. 138 and is scheduled to start on S.R. 112 next week. Lane restrictions on S.R. 112 will take place during non-commute times between 7 a.m. and 10 p.m. One lane will be open to one direction of travel at a time, with one-way flagging operations. Drivers can expect delays and travel on uneven pavement surfaces.

Area residents and businesses can expect temporary intermittent closures of side streets as paving work passes through the area. Travelers, area residents, and businesses can expect construction-related noise, dust, and minor travel delays.

 

CONTACT US

Questions? Concerns? Our dedicated public involvement team is here to help. Please feel free to call the project hotline at (435) 213-1637 or email us at SR112andSR138@utah.gov. In addition, check the project websites for more information: udot.utah.gov/go/sr138 | udot.utah.gov/go/sr112

Stay up to date with upcoming construction projects in the area by following the UDOT Tooele Valley Construction Projects Facebook page.

Please note that construction schedules are subject to change due to weather or equipment-related issues.

 


Updated June 22, 2021

***Pavement work on S.R. 112 (1000 North) is scheduled to begin this week with full closures of the 600 W. and 200 W. intersections.***

The S.R. 112/600 W. intersection is scheduled for a full closure from Friday, June 25 through Sunday, June 27. The S.R. 112/200 W. intersection is scheduled for a full closure from Friday, July 9 through Sunday, July 11.

One-way flagging operations will be in place. Drivers can expect delays when traveling through the area and are encouraged to use alternate routes such as S.R. 138 and S.R. 36. Work is expected to continue through the fall.

 

S.R. 138 PROJECT UPDATE

Paving work on S.R. 138 is now complete. To reduce traffic-related noise for area residents, crews have permanently removed the rumble strips along S.R. 138 between S.R. 36 and Castle Rock Drive.

Brief, intermittent lane closures for permanent striping, utility work and signage installation is scheduled to occur on weekdays during non-commute times between 8 a.m. and 4 p.m. Drivers can expect minor delays when traveling through the area.

 

FREEWAY CLOSURE NOTICE

I-80 drivers should plan for overnight closures of the freeway the week of June 21st. Crews will be setting girders (bridge supports) for the Midvalley Highway bridge over I-80 as they construct a new interchange.

Westbound I-80 will close completely at the exit 99 interchange Monday, Tuesday and Wednesday evenings from 8 p.m. to 5 a.m. nightly.

Eastbound lanes will close nightly Thursday, Friday and Saturday from 8 p.m. to 5 a.m. at exit 84.

Drivers will be directed onto S.R. 138 and S.R. 36 as detours.

If you have any questions or concerns, please contact the Midvalley Highway public involvement team at midvalley@utah.gov or by calling the project hotline number at (435) 557-0409.

 

PROJECT INFORMATION:

UDOT is dedicated to investing in the community by renewing the pavement on S.R. 138 and S.R. 112. This work will improve safety, reduce traffic-related noise and provide a more enjoyable ride for all area residents and businesses.

Paving work is now complete on S.R. 138 and is scheduled to start on S.R. 112 next week. Lane restrictions on S.R. 112 will take place during non-commute times between 8 a.m. and 4 p.m. One lane will be open to one direction of travel at a time, with one-way flagging operations. Drivers can expect up to 15-minute delays and travel on uneven pavement surfaces.

Area residents and businesses can expect temporary intermittent closures of side streets as paving work passes through the area. Travelers, area residents, and businesses can expect construction-related noise, dust, and minor travel delays.

 

CONTACT US:

Questions? Concerns? Our dedicated public involvement team is here to help. Please feel free to call the project hotline at (435) 213-1637 or email us at SR112andSR138@utah.gov. In addition, check the project websites for more information: udot.utah.gov/go/sr138 | udot.utah.gov/go/sr112

Stay up to date with upcoming construction projects in the area by following the UDOT Tooele Valley Construction Projects Facebook page.

 

Please note that construction schedules are subject to change due to weather or equipment-related issues.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Copyright © 2021 Utah Department of Transportation, All rights reserved.

 

Our mailing address is:

UDOT Region Two

2010 South 2760 West

Salt Lake City, UT 84104