SR-36 (Tooele’s Main Street) Construction Project

SR-36 RENEWED

 Route
SR-36:  3 O’Clock Drive to Stansbury
 Description

Watch the Project Video!Beginning Monday, March 23, 2015, Tooele City’s contractor will be replacing a 12-inch water main in Main Street between Canyon Road (approximately 650 South) and 600 North.  Click Here for more information about this project.

The Utah Department of Transportation (UDOT), in coordination with Tooele City, is designing the full pavement reconstruction of SR-36 from 3 O’Clock Drive to 1280 North and pavement rehabilitation (rotomill and overlay) from 1280 North to Stansbury Parkway. Once the project is complete, the pavement life will be extended and the corridor will have consistent features that enhance safety.

WATCH THIS VIDEO FROM UDOT for a complete project description!

The project includes the following major items of work:

3 O’CLOCK DRIVE TO 1280 NORTH

• Remove and replace pavement section
• Install new storm drain
• Replace deficient curb, gutter and sidewalk
• Upgrade pedestrian ramps to meet ADA standards
• Complete utility work to accommodate road work
• Tooele City’s waterline replacement project from Old Canyon Road to 600 North (this work will take place prior to the road construction)

1280 NORTH TO 2000 NORTH

• Remove and replace the top 1″ of pavement
• Install curb and gutter on east side of road
• Complete drainage improvements on east side of road

2000 NORTH TO STANSBURY DRIVE

• Remove and replace the top 1″ of pavement

 

 Community Notices
The project team will be presenting to the Tooele City Council on Wednesday, March 4th at 7pm.  A public open house will be held the same evening at Tooele City Hall (90 N Main) from 6pm-9pm.  Please attend to view project information, schedule and the traffic and access plan for during construction.
 Schedule
• Proposed Advertised Date – March 2015
• Proposed Construction Start Date – June 2015
 Contact Information
Carlye Sommers
Public Involvement Manager
801-859-3770
SR36@utah.gov