SR-36 Renewed (08/17/15 – 08/24/15)

The following information and images are provided by UDOT.

      

Crews working on utility lines at the 1000 North intersection.

SR-36 Renewed

Resurfacing work from 2000 N to Stansbury begins 8/19

This work will take approximately 2 months to complete and will involve removing and replacing the top layer of asphalt. This work will not include a full reconstruction of the roadway like the work currently taking place south of 1280 North.

For approximately two weeks crews will be replacing damaged or deteriorating concrete at cross streets and along the median barrier.  This work will include daytime shoulder closures.

Once the concrete work is complete, crews will begin removing asphalt.  This work will take place at night and will reduce traffic to one lane in each direction during the following times:

  • Southbound traffic reduced to one lane from 8pm to 7am
  • Northbound traffic reduced to one lane from 7pm to 5am

Road Closures

1000 North East Side Reopens 8/18

Our crews will reopen the east side of the 1000 North intersection on Tuesday, August 18.  Paving will not have been completed by that time so traffic on the east leg of the intersection will be on gravel.  Paving is scheduled to take place two days later on Thursday, August 20.  During paving the intersection will remain open but will be shifted to the north and south as needed to accommodate the paving crews.

200 North (Utah Avenue) No Closure Tonight

The 200 North (Utah Ave.) intersection will not be closed this evening.  CenturyLink will need an additional two night closure of the full intersection and an additional one day closure of the east leg of the intersection to remove supports placed on their communication line but these closure dates have not yet been determined.

600 North Access Closed 8/14 from 7 a.m. to 7 p.m.

Access to and from 600 North from SR-36 will be closed on Friday, August 14 from 7 a.m. to 7 p.m.  This closure will accommodate the placement of the storm drain across 600 North.

During this closure, traffic should use 500 North or 700 North as alternates.

Upcoming Work – 8/17/15 to 8/24/15

Railroad Bridge to 1000 North

  • Crews will complete the concrete work on the east side by 8/21.
  • Installation of curb and gutter on the west side will continue through 8/21.
  • Paving on the west side from 1280 North to 1000 North will begin on 8/19.
  • Traffic restrictions for this area include:
    • Northbound and southbound traffic is reduced to one lane in each direction.
    • East leg of the 1000 North intersection will be closed through 8/18
    • Paving on Pine Canyon Road will take place later this month.  This work will be done with flagging operations rather than a full closure.
    • Left turns are prohibited at:
      • 1280 North
      • 1000 North

1000 North to 600 North

  • 600 North will be closed Friday, August 14 from 7 a.m. to 7 p.m. to accommodate the placement of the storm drain across 600 North.
  • Curb and gutter placement from 1000 North to 600 North will continue through late August.
  • Paving will begin on 8/19.
  • Traffic restrictions for this area include:
    • Northbound and southbound traffic is reduced to one lane in each direction
    • 600 North intersection will be closed 8/14
    • Left turns are prohibited at:
      • 1000 North
      • 700 North
      • 600 North

600 North to 200 North

  • Storm drain placement will continue in this section next week; work is anticipated to reach approximately 300 North. This work will include open trenching and the use of heavy machinery.  Driveway access changes will be coordinated with property owners.
  • Crews will begin hauling in materials once the storm drain is placed. Use caution when accessing driveways and cross streets as large trucks and heavy machinery will be used during this operation
  • Traffic restrictions for this area include:
    • Northbound and southbound traffic is reduced to one lane in each direction
    • Left turns are prohibited at:
      • 500 North
      • 400 North
      • 200 North

200 North to 520 South

  • Crews will begin the storm drain in this section next week. Storm drain installation will progress at a rate of approximately 300′ per day. Work will include open trenching and the use of heavy machinery. Driveway access changes will be coordinated with property owners.
  • Utility relocation and grading work will take place south of the storm drain installation.
  • Traffic restrictions for this area include:
    • Northbound and southbound traffic is reduced to one lane in each direction
    • Lefts are prohibited at Vine Street

Questions or Concerns

If you have any questions or concerns about the project, please contact UDOT.  They are available 24 hours a day and are happy to assist you. You can reach them by phone, text, email or Twitter (see below).

UDOT’s Contact Information:

Phone or Text: 801-859-3770
Email: sr36@utah.gov
Web: www.udot.utah.gov/go/sr36