Temporary striping has been placed from 1280 N to 1000 N; A crew member delivers storm drain pipe at 600 North.
 

SR-36 Renewed

Pioneer Day Holiday

Crews will not be working Friday, July 24 through Sunday, July 26.  Work will resume at 7 a.m. on Monday, July 27. We hope everyone enjoys a happy and safe holiday weekend.

Upcoming Work – 07/20/15 – 07/27/15

Railroad Bridge to 1000 North

  • Beginning 7/27, traffic will be moved to the east side of SR-36 on new pavement.  Crews will then begin excavating the west side of the road.
  • Traffic restrictions for this area include:
    • Northbound and southbound traffic is reduced to one lane in each direction except from 7/24 to 7/27.
    • Flagging operations will be used intermittently on Pine Canyon Road, from UEC Movie Theater to Copper Canyon Drive, through late July.  One additional one-day closure of Pine Canyon Road will be needed to complete asphalt paving but this work has not yet been scheduled.
    • Left turns are prohibited at:
      • 1280 North
      • 1000 North

1000 North to 600 North

  • Flaggers will be used at the 600 North intersection to accommodate the relocation of a Comcast line beginning 7/27 and lasting approximately three days. Once complete, the flagging operation will move to the 500 North intersection.
  • Storm drain placement will continue moving south next week; work is anticipated to reach approximately 600 North. This work will include open trenching and the use of heavy machinery.  Driveway access changes will be coordinated with property owners.
  • Traffic restrictions for this area include:
    • Northbound and southbound traffic is reduced to one lane in each direction
    • Left turns are prohibited at:
      • 1000 North
      • 700 North
      • 600 North

600 North to 200 North

  • Crews will continue to work in the excavated area from 600 North to 200 North to relocate utilities and prepare the subgrade for road base placement.
  • Traffic restrictions for this area include:
    • Northbound and southbound traffic is reduced to one lane in each direction
    • Left turns are prohibited at:
      • 500 North
      • 400 North

200 North to 520 South

  • Crews will continue excavating the old road subgrade materials and preparing for the placement of new subgrade materials.
  • Traffic restrictions for this area include:
    • Northbound and southbound traffic is reduced to one lane in each direction

Business Access

  

Please remember to use the designated access points for businesses along SR-36. These driveways are marked with business access signs to assist drivers.  Also, we encourage everyone to use 50 East and 50 West to access businesses whenever possible.  This helps reduce the number of cars within the work zone and gets you to your destination faster.

Questions or Concerns

If you have any questions or concerns about the project, please contact UDOT.  They are available 24 hours a day and are happy to assist you. You can reach them by phone, text, email or Twitter (see below).

UDOT’s Contact Information:

Phone or Text: 801-859-3770