SR-201 Improved (Updated 09/11/17)

Construction work will be finishing up on SR-201 in Salt Lake City between I-80 and 9200 West.  Motorists can expect construction crews in the area through Friday, September 15.

The construction crews will be completing the following activities next week:

• Traffic will continue to be shifted intermittently for utility and shoulder work, sign installation, and striping operations that will occur throughout the project area.

• Construction crews will continue removing and installing new barrier and guardrail throughout the corridor.

Motorists should expect up to a maximum of 15 minute delays during work hours. Traffic will be impacted during construction times:

• During morning peak hours Monday through Friday (6 a.m. to 9 a.m.) two lanes of traffic will be open going eastbound on SR-201.

• During evening peak hours Monday through Friday (3 p.m. to 6:30 p.m.) two lanes of traffic will be open going westbound on SR-201.

• During off peak hours there will be one lane of road open in each direction.

Updated information is available at www.udot.utah.gov/go/SR201 or by emailing SR201@utah.gov.  Stakeholders can also call the project hotline at (801) 707-3662.


The Utah Department of Transportation (UDOT) continues working on a repaving and barrier project in Salt Lake City on SR-201. This project will extend the roadway’s life, improve the ride and increase safety of the roadway. This is part of UDOT’s mission to be proactive in the preservation of the current infrastructure.

OVERVIEW
• Construction work will begin July 25 and is expected to be completed September 15.
• Work will occur Monday through Saturday, 7 a.m. to 7 p.m.
• Construction areas on SR-201 will be between I-80 and 9200 West.